Newport Bus Priority Measures, A48 Cardiff Road, Newport

Client: Newport City Council
Contract Value: £303,000.00
Construction Period: 14 weeks
Involved the removal of an existing roundabout and the installation of traffic lights on a major junction of the A48 outside the Royal Gwent Hospital.
Toucan Crossing, Wharf Road, Newport

Contract Value: £47,000.00
Construction Period: 8 weeks
This involved the installation of a new controlled pedestrian crossing across a busy dual carriageway.
Merthyr Tydfil Pedestrian Crossing Improvements
Client: Merthyr Tydfill County Borough Council
Contract Value: £60,000.00
Construction Period: 5 weeks
This involved replacement of traffic signals on pedestrian crossings at numerous locations around Merthyr Tydfil. The old signals were removed and the new installations erected with associated tactile paving and kerbs with as little disruption as possible.